Premier visits Frankston Redevelopment projectPremier Tours Frankston Redevelopment Site

12 April, 2023

As work continues on the $67.6 million Frankston Redevelopment Project, Premier Daniel Andrews and Minister for Training and Skills Gayle Tierney were on site last week with Member for Frankston Paul Edbrooke to view the amazing progress. Accompanied by Chisholm Board Chair Prue Digby, CEO Stephen Varty, and Director, Infrastructure and IT, Richard Pratten, the group were led on a tour encompassing all three levels of the future state of the art facility.

With the structural steel and building core near completion and the third-floor slab now in place the group were able to see some of the building’s core features taking shape. Work on internal walls and services rough-in continues, with the building expected to be watertight in the next 6 weeks. Once this milestone is achieved the team will turn their focus to the internal fit out.

Frankston Minister visit to Chisholm Frankston campusMinister for Frankston visits Chisholm worksite

3 April, 2022

State Member for Frankston Paul Edbrooke joined Chisholm’s CEO Stephen Varty and Director - Infrastructure and IT, Richard Pratten on site this month to view the progress being made on Stage 2 of the Frankston Redevelopment Project. Concrete works continue with the slabs on all three floors due for completion by Easter. Façade and roofing works will then commence with the building expected to reach lock-up stage in June.

Chisholm Board Tours Frankston Redevelopment SiteChisholm Board Tours Frankston Redevelopment Site

2 December, 2022

Members of Chisholm’s Board were on site this week for a tour through Stage 2 of the Frankston Redevelopment Project. Led by Kane Construction’s Senior Project Manager, John Moran, the group inspected the ground level infrastructure before moving up to level 2 to better see how the building will fit into the surrounding campus grounds. There was an opportunity to visualise the planned atrium space at the centre of the new building and to further discuss some of the construction techniques being implemented on site. The tour showcased the great progress that has been made on site to date and provided a sneak-peek at some of the key features of the build.

Chisholm staff at the first pourFirst Concrete Pour – Frankston Redevelopment Stage 2

 11 August, 2022

Despite the rain, acting Chisholm CEO Toniann Stitz visited the Frankston Campus last week to check the progress of the first slab pour at the Frankston Redevelopment Stage 2 site. Infrastructure & IT Director Richard Pratten, and Head of Campus Services & Infrastructure Lisa Speakman were also in attendance as the first of four slabs making up the ground floor of the new Building C was poured. The visit marked a significant milestone in the project’s construction as we finally begin to see Stage 2 rise from the ground.

Conceptual drawing of Building C façade showing external landscaping and courtyardBreaking Ground on a New Era at Chisholm Institute Frankston

 22 April, 2022

On Friday 22 April we broke ground on Stage 2 of the Frankston Redevelopment Project. Victorian Premier Daniel Andrews, The Minister for Training and Skills, and the State Member for Frankston were joined by Stephen Varty, Stephen Marks and local officials in a ceremonial Sod Turn to mark the occasion.

Read Breaking Ground on a New Era at Chisholm Institute Frankston

Conceptual drawing of Building C façade on Fletcher RoadChisholm Welcomes Frankston Campus Stage 2 Funding

27 November, 2020

The Victorian Government has officially confirmed their investment in the second stage of the Frankston campus redevelopment. The Minister for Training and Skills, the Hon. Gayle Tierney was on campus today to make the exciting announcement.

Read Chisholm Welcomes Frankston Stage 2 Funding